SHIP CONSTRUCTION HEAVY LIFT BARGE SURREY, BC. This ship construction project
required the lengthening of the barge, welding of additional fabricated units
to the existing structure, and the installation of a 600 ton lifting
capacity crane to the new extension. The first phase of the
project commenced in April 2005 for the pre-fabrication of the steel panels
at Meridian Marine's workshop. In August, the pre-fabricated panels were
delivered to the customer's site where our team of steel fitters and welders
worked to complete the installation phase of the project, reaching completion
in October 2005.